The recent challenging weather isn’t slowing Tru by Hilton down. The vibrant colored EIFS exterior is starting to be installed, broadcasting an eye-catching appearance to passing by spectators. Meanwhile, drywall and painting is finishing up inside along with the pool installation, making way for the ceramic tiling in the bathrooms and natatorium. MEP fixtures continue to be installed, followed by the bathroom accessories, acoustical ceilings, LVT flooring, carpet, and PTAC units. Hilton is scheduled to inspect the hotel in the middle of April, followed by the fixtures, furnishings, and equipment installation. Final punch list items will start in May prior to Hilton’s final inspections, opening in time for the busy summer months.